May 2020 Bond Update


Phase I: Athletic Field, Track, Event Areas, & Lighting

Improvements Include:

    • New synthetic field turf for the athletic playing surface
    • New track & event areas
    • Fencing & ADA compliant sidewalk around track surface
    • LED lighting for athletic field

Proposed Timeline: Construction has begun and is scheduled to end 8/25/2020

Phase II: Early Childhood Center Construction, Renton Renovations, & Renton Addition

Improvements Include:

    • New Early Childhood Center, complete with furnishings.This includes new classrooms, officeslibrary space, restrooms, kitchen, storage, & athletic gym/cafeteria.
    • Renton Renovations: Secured Entry Renovation, lockers, restrooms, PA/Clocks, drinking fountains, flooring, lighting, electrical, mechanical, plumbing, , interior and exterior doors, & new roof
    • Renton Science Classrooms & Restroom Addition

Proposed Timeline: New Construction is scheduled to begin May 2020 and end June 2021. Renovations are scheduled to begin mid-June 2020 and end September 2020.

Phase III: Miller & Brown Renovations & Additions

Improvements Include:

    • Building Renovations: Secured Entry Renovation, restrooms, PA/Clocks, drinking fountains, flooring, lighting, electrical, mechanical, plumbing, interior and exterior doors, new roof, & parking renovations.
    • New Classroom Additions to each building, complete with furnishings.

Proposed Timeline: The Phase III construction scheduled is currently being planned as part of the design and development process.

Phase IV: Huron High School and Bus Garage Renovations

Improvements Include:

    • High School Building Renovations: Secured Entry Renovation, new science labs, STEM center,  lockers, locker commons, restrooms, PA/Clocks, drinking fountains, flooring, lighting, electrical, mechanical, plumbing, interior and exterior doors, new roof, & parking renovations.
    • Bus Garage Renovations:Restroom renovations and replacement of bus railing barrier.

Renderings


Bond Science Lab Rendering

Bond Kindergarten Class Rendering

Bond Rendering Poster

Bond Rendering Poster 2

Posted by admin  On May 15, 2020 at 1:17 PM
  

Thanks to all of Huron's teachers for doing an incredible job and to all the students and families that have shown their support this week!

2020 Teacher Appreciation Week

Posted by admin  On May 08, 2020 at 2:49 PM